Mistakes that sink new contractors

Almost every estimating disaster is one of seven mistakes. Learn them now so you never learn them the expensive way.

In this series

The seven

The mistakeWhat it costs youThe fix
Pricing labor at the raw wageLoses the whole burden, often 30–50%Always use the burdened rate (chapter 6)
Confusing markup with marginYou keep far less profit than you thinkSet margin first, back into markup (chapter 7)
Forgetting overhead in the markupYour "profit" quietly pays your bills insteadMarkup covers overhead and profit
Missing items in the takeoffYou eat every forgotten materialWork systematically, check off the plan (chapter 4)
No contingency or allowancesEvery surprise comes out of profitPrice the unknowns on purpose (chapter 8)
Underbidding to winYou "win" a money-losing jobBid your real number, walk from bad prices
No written scope in the proposalDisputes and unpaid extrasSpell out included and excluded (chapter 9)

What they have in common

Six of the seven are silent. Nothing goes wrong at bid time. You find out months later, when the job is finished and the money isn't there. That's what makes a checklist worth more than good instincts here, and why the The quick-reference pack ends with one.